Select Region:

Related Links:

  • No related links at this time

West Oregon - Local Events


Benton County


27017 Hubbard Rd, Monroe, OR 97456

Construction - Substantial Delays
Direction Impacted: East, West
Traffic Control: No Through Traffic
Comments: Bridge is closed until further notice. County is applying for grant to replace bridge. Bridge may be opened to light traffic during flooding events.
Public Contact: Laurel Byer
Phone: (541) 766-6821
Updated: Aug 16, 2016 4:50 PM


Eugene


W. 2nd Avenue at Garfield Street to W. 2nd Avenue at Blair Blvd

Construction - Minimal Delays
Direction Impacted: East, West
Traffic Control: Lanes Closed
Comments: Roadway excavation, storm pipe work and concrete replacement will cause some lane closure Monday through Friday. Watch for flaggers, use alternate routes and expect delays of up to 10 minutes. Additionally, expect closure of W. 3rd Avenue and Lawrence Street at railroad tracks and northeast corner parking lot during same work.
Public Contact: Public Works Engineering
Phone: (541) 682-5291
Updated: May 05, 2017 2:44 PM

Click here for additional information


W. 1st Avenue at Chambers Street to W. 1st Avenue at Blair Blvd

Construction - Minimal Delays
Direction Impacted: East, West
Traffic Control: Lanes Closed
Comments: Excavation and concrete panel work will take place Monday through Friday. Expect lane closures and minor delays. Watch for flaggers, use alternative routes if possible and expect delays of up to 10 minutes.
Public Contact: Public Works Engineering
Phone: (541) 682-5291
Updated: May 05, 2017 2:42 PM

Click here for additional information


3rd Avenue at Lincoln Street to 3rd Avenue at Washington Street

Construction - Substantial Delays
Direction Impacted: East, West
Traffic Control: Lanes Closed
Comments: 3rd Avenue will be closed from Lincoln to Washington streets until mid-May. There will be times that one-way traffic is open, but it will be sporadic. Crews are building the street.
Public Contact: Teri Higgins
Phone: (541) 682-5291
Updated: Apr 19, 2017 1:00 PM

Click here for additional information


Lane County


827 W 6th Ave, Eugene, OR 97402

Construction - Substantial Daytime Delays
Direction Impacted: East, West
Traffic Control: Traffic Flow Change
Comments: West Eugene EmX Extension - from Charnelton Street to Garfield Street on West 6th Avenue. To sign-up for updates visit; https://www.ltd.org/west-eugene-emx/ Click the link below for detailed information and updates on project construction.
Public Contact: Lisa VanWinkle
Phone: (541) 682-6212
Updated: Dec 21, 2015 10:39 AM

Click here for additional information


3404 W 11th Ave, Eugene, OR 97402

Construction - Substantial Daytime Delays
Direction Impacted: East, West
Traffic Control: Traffic Flow Change
Comments: West Eugene EmX Extension - from Garfield Street to Beltline Road on West 11th Avenue. To sign-up for updates visit; https://www.ltd.org/west-eugene-emx/ Click the link below for detailed information and updates on project construction.
Public Contact: Lisa VanWinkle
Phone: (541) 682-6212
Updated: Dec 21, 2015 10:39 AM

Click here for additional information


112 W 11th Ave, Eugene, OR 97401

Construction - Substantial Daytime Delays
Direction Impacted: East, West
Traffic Control: Traffic Flow Change
Comments: West Eugene EmX Extension - from east of Willamette Street to Charnelton Street along West 11th Avenue. Click the link below for detailed information and updates on project construction.
Public Contact: Lisa VanWinkle
Phone: (541) 682-6212
Updated: Apr 30, 2015 12:44 PM

Click here for additional information


864 Charnelton St, Eugene, OR 97401

Construction - Substantial Daytime Delays
Direction Impacted: North, South
Traffic Control: Traffic Flow Change
Comments: West Eugene EmX Extension - from West 6th Avenue to West 11th Avenue on Charnelton Street. Click the link below for detailed information and updates on project construction.
Public Contact: Lisa VanWinkle
Phone: (541) 682-6212
Updated: Apr 30, 2015 12:41 PM

Click here for additional information


W 7th Ave, Eugene, OR 97402

Construction - Substantial Daytime Delays
Direction Impacted: East, West
Traffic Control: Traffic Flow Change
Comments: West Eugene EmX Extension - from Charnelton Street to Garfield Street on West 7th Avenue. Click the link below for detailed information and updates on project construction.
Public Contact: Lisa VanWinkle
Phone: (541) 682-6212
Updated: Apr 30, 2015 12:36 PM

Click here for additional information


Springfield, Oregon


Mississippi Ave to intersection of Franklin Blvd and McVay Hwy

Construction - Minimal Delays
Direction Impacted: East, West
Traffic Control: Traffic Flow Change
Comments: Construction of the first phase of New Franklin Blvd improvements is underway mid-May 2017 through fall 2018. The intersection of Franklin Boulevard and South Franklin (McVay Highway 225) will be closed to turns. Franklin Boulevard will be open to eastbound and westbound travel. Construction will take place between 7 am and 6 pm, Monday through Friday. Businesses will remain open and accessible. Businesses located on South Franklin Boulevard near the intersection with Franklin Boulevard can be accessed using a detour via Henderson Avenue and E 19th Avenue. Construction will include grading, drainage, paving, signing, lighting, roundabouts, sidewalks, and bike facilities on Franklin Blvd in Glenwood from Mississippi to McVay Hwy. To receive periodic project updates send an email to info@newfranklinblvd.org and include your name.
Public Contact: Kristi Krueger
Phone: (541) 726-4584
Updated: May 01, 2017 5:11 PM

Click here for additional information

TripCheck is on Twitter.  Get more information. The OReGO Interest List