Willamette St between 8th Ave and 7th Ave

Construction - High Impact
Comments

Excavation and concrete work will be ongoing at the northwest corner of Willamette St and 8th Ave. The southbound lane along Willamette St will be closed between 7th Ave and 8th Ave while the contractor rebuilds the sidewalk access ramp. The northbound lane will remain open, southbound between 8th Ave and Broadway will remain open, and 8th Ave will remain open.

 

Expect the southbound lane closure and traffic delays, southbound traffic is encouraged to use Charnelton St or Pearl St. 

Cyclists are encouraged to use Pearl St or Olive St. 

Pedestrians are encouraged to use the east side of the street between 7th Ave and 8th Ave. 

Please be aware of large trucks and equipment in the area.

 

This work is part of the larger 8th Ave project.

Public Contact
Rachael Love
City of Eugene
Phone: (541) 501-0379
Email: RLove@eugene-or.gov
Event Id
4102
Updated
4/16/2024 9:27 AM

Charnelton St, Northbound Lane

Construction - Moderate Impact
Comments

The northbound lane along Charnelton St will be closed between 7th Ave and Broadway St until the concrete street reaches enough strength to support vehicle traffic. The southbound lane will remain open and 8th Ave will remain open.


Expect the northbound lane closure and traffic delays, northbound traffic is encouraged to use Lincoln St. Cyclists are encouraged to use Lincoln St, Olive St, or Pearl St. Sidewalks and access ramps are fully open to pedestrians. 

 

This work is part of the larger 8th Ave project.

Public Contact
Rachael Love
City of Eugene
Phone: (541) 501-0379
Email: RLove@eugene-or.gov
Event Id
4101
Updated
4/16/2024 9:25 AM

Chambers from 18th to 24th

Construction - Moderate Impact
Direction Impacted
Both
Comments

Construction will continue on Chambers Street this week. The scheduled work consists of adjusting manholes to match the elevation of the new pavement. For this week, no vehicle lane closures are scheduled. Vehicle traffic should expect lane shifts marked by traffic cones throughout the work zone. Street parking will be limited throughout. Bicycles will be detoured through Westmoreland Park. Pedestrian crossings and sidewalks will remain open this week.

Public Contact
Jennah Maier
City of Eugene
Phone: (541) 852-2227
Email: JMaier@eugene-or.gov
Event Id
4100
Updated
4/16/2024 9:22 AM

13th and Adams

Construction - Moderate Impact
Comments

Northbound lane will be closed for concrete repair. Lane will remain closed for the duration of the work. Drivers should watch for signs.

Public Contact
Davena Amick-Elder
City of Eugene
Phone: (541) 682-4806
Email: DAmick-Elder@eugene-or.gov
Event Id
4099
Updated
4/16/2024 9:19 AM

Enhanced Walking Network

Construction - Moderate Impact
Direction Impacted
Both
Comments

This project is intended to enhance walking and bicycling connectivity throughout Eugene. 


Ongoing water transmission main and Storm water main construction will limit all but local access between E 34th and E 40th. Local vehicular access is encouraged via Donald St and 40th 39th and 36th. Pedestrian access on Hilyard is open on the west sidewalk to Tugman Park. Watch for large trucks and construction equipment on site.

Public Contact
Bryan Root
City of Eugene
Phone: (541) 501-0378
Email: bryan.D.Root@ci.eugene.or.us
Event Id
4093
Updated
4/16/2024 8:55 AM

8th Avenue Streetscape Project

Construction - High Impact
Comments

The project will repave sections of 8th Avenue from Lincoln Street to Mill Street, convert the section to a two-way street, construct protected bike lanes from High Street to Lincoln Street, add 4-way stops at key intersections, and widen sidewalks and reconstruct sidewalk access ramps. 


Motor vehicle parking on the south side of 8th Avenue will be removed and parking on the north side will be relocated away from the curb, to allow for the protected bike lanes. The project aims to create a safe travel option for community members of all ages and abilities to access Downtown Eugene.


Expect periodic closures and equipment and workers in the roadway. Follow signed detours.

Public Contact
Rachael Love
City of Eugene
Phone: (541) 501-0379
Email: RLove@eugene-or.gov
Event Id
4091
Updated
4/16/2024 8:54 AM

Leo Harris Parkway at Martin Luther Junior Blvd West Entranc

Construction - Low Impact
Comments

West entry/exit of Leo Harris Parkway at MLK closed for construction from 4/3 through 4/25. Leo Harris Parkway East entrance past the Stadium is open for access to the stadium and related facilities. Entrance to the Eugene Science Center is closed. Pedestrian access is open on the west side of Leo Harris and access on MLK is open for East /West Pedestrian travel. Bikes are encouraged to use the East Leo Harris entrance.

Public Contact
Bob Pappalardo
City of Eugene
Phone: (541) 246-4728
Email: Bpappalardo@eugene-or.gov
Event Id
4094
Updated
4/16/2024 8:54 AM

Green Hill Rd Bridge #039C51

Construction - Low Impact
Comments

Lane County will be performing bridge rail repairs on Green Hill Rd Bridge starting April 9th, 2024. The project contract end date is June 30, 2024. Traffic will be controlled by flaggers. Please obey the traffic control signs, use caution and slow down through work zones to improve safety and efficiency.

Public Contact
Derek Jensen
Lane County Public Works Engineering & Construction Services
Phone: (541) 682-6929
Email: ecs-construction@lanecountyor.gov
Event Id
4086
Updated
4/08/2024 8:21 AM

N Game Farm Rd M.P. 0.59 to M.P. 1.69

Construction - Low Impact
Comments

Lane County will be upgrading ADA curb ramps, paving, signing and doing traffic signal modifications on N Game Farm Rd, starting February 20, 2024. The project contract end date is December 31, 2024. Please obey the traffic control signs and flaggers. Please use caution and slow down through work zones to improve safety and efficiency.

Public Contact
Derek Jensen
Lane County Government
Phone: (541) 682-6929
Email: ecs-construction@lanecountyor.gov
Event Id
4029
Updated
2/05/2024 2:29 PM

South 28th St., Springfield, OR

Construction - Low Impact
Comments

Lane County in partnership with City of Springfield will be installing storm sewer facilities, grading, and paving along S 28th St, from F St. heading south for approximately 1500 ft. Construction work starts on January 17th, 2024 and the project contract end date is December 31, 2024. Please obey the traffic control signs and flaggers. Please use caution and slow down through work zones to improve safety and efficiency.

Public Contact
Derek Jensen
Lane County Public Works Engineering & Construction Services
Phone: (541) 682-6929
Email: ecs-construction@lanecountyor.gov
Event Id
3937
Updated
1/11/2024 10:34 AM